Projects with DPR Under Progress


 

Status of Port Connectivity Projects

S. no.

State

Project Stretch

Name of Port/ IWT Terminal Connected

Length (km)

Total Capital Cost (INR Cr.)

Mode of Implementation (Tentative)

Total Fund required (100% of TPC for EPC projects and 40% of TPC for HAM projects)

Status

1

Andhra Pradesh

2 to 4 laning of road connecting Kakinada port to NH 16 at Rajanogaram in Godavari District (Samalkota to Achampeta junction)

Kakinada Port

13

595

EPC

595

DPR in progress. LAC proposal is likely to be submitted by 15th July.

2

Andhra Pradesh

Four lane Green field road connecting North & South Industrial cluster of Khandaleru creek near Krishnapatnam port at Thamminapatnam to Mollur and extension of Dedicated port road on NH-67 in the state of Andhra Pradesh from 18 km to 19.300 (Pkg III)

Krishnapatnam

17

584

EPC

584

DPR completed. LAC approved the alignment. PATSC proposal prepared, the same shall be sumitted after publication of 3(A). Likely date 15th July.

3

Andhra Pradesh

4 lane road to Krishnapatnam Port from Naidupeta in AP (Pkg-IV)

Krishnapatnam

35

1,254

HAM

502

DPR completed. LAC approved the alignment. PATSC proposal prepared, the same shall be sumitted after publication of 3(A). Likely date 15th July.

4

Andhra Pradesh

4 laning of Kakinada Anchorage Port Uppada beach road connecting NH-16 in East Godavari District

Kakinada Anchorage Port

40

1,381

HAM

552

DPR completed. 3(A) published. Proposal likely to be submitted by 15th July for appraisal.

5

Andhra Pradesh

Construction of 4-laning of Chilakaru cross road to Turpu Kanupuru, Km.0.00 to (Km.131.500 of NH-16) to Km.23.717 including flyovers & approaches on NH-16 (1.05 Km) and 6-laning of Turpu Kanupuru  to Port South Gate from Km.0.00 to Km.11.245 Pkg - II

Krishnapatnam

36

917

HAM

367

DPR completed. LAC approved the alignment. PATSC proposal prepared, the same shall be sumitted after publication of 3(A). Likely date 15th July.

6

Andhra Pradesh

Improvement/upgradation of four lane road to six lane road for the port connectivity road from East Breakwater to Sheela Junction

Vishakhapatnam

11

275

EPC

275

DPR in progress. Alignment is to be approved by VPT.

7

Andhra Pradesh

Improvement works for Visakhapatnam Port Road

Vishakhapatnam

13

160

EPC

160

DPR in progress. Details of improvement are under discussion with VPT.

8

Andhra Pradesh

4 laning of road from Nellore city to Krishnapatnam port to NH 5

Krishnapatnam

24

600

EPC

600

DPR in progress. Proposal likely to be submitted for appraisal by 30th Aug.

9

Andhra Pradesh

Development of coastal 4 lane highway port connectivity project connecting Vizag port terminal with NH16 to Bhogpuram via Rishikonda and Bheemili

Vishakhapatnam

65

1,560

HAM

624

DPR in progress. Consent of State Govt. is yet to be received.

10

Andhra Pradesh

Development of Fly over bridge from  Sea-horses junction area to dock area at Vizag Port

Vishakhapatnam

4

255

EPC

255

DPR in progress. Proposal is likely to be submitted by 30th July for appraisal.

11

Andhra Pradesh

Construction of flyover / under pass at Vizag airport junction to ensure flow of container trailers to/from MMLP setup at NH-16

Vishakhapatnam

5

28

EPC

28

DPR in progress. Proposal is likely to be submitted by 15th Aug for appraisal.

12

Karnataka

Yekkambi-Haveri (Sirsi-Yekkambi-Haveri)

Belekeri

75

296

EPC

296

DPR completed.  Proposal likely to be submitted by 15th July for appraisal.

13

Karnataka

By pass road from NH to Belekeri Port and rail connectivity from Harwada to Belekeri

Belekeri

7

175

EPC

175

DPR in progress.  Proposal likely to be submitted for appraisal by 30th July.

14

West Bengal

Double Lane to 4 Lane road connecting Haldia Multi Modal Terminal and NH-116 (National Waterway-1)

Haldia MIT

6

1,307

EPC

1,307

DPR in progress.

15

West Bengal

Two Lane to Four lane road connecting Kolaghat to NH-41 (national Waterway-86)

Kolaghat

4

254

EPC

254

DPR in progress.

16

Odisha

Construction of bypass road from NH-16 to Gopalpur port

Gopalpur

12

156

EPC

156

DPR in progress. LAC proposal is likely to be submitted by 30th Aug.

17

West Bengal

Improvement of existing road connecting Kolkata Port Trust to NH6 and Kolkata Port Trust to nearly industrial Clusters

Kolkata

6

150

EPC

150

DPR in progress.

18

Kerala

Development of river side port road to Beypore port

Beypore

2

50

EPC

50

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

19

Kerala

Azhikkal Port - Proposed NH – Bypass and widening of 2 km.

Azhikkal

13

325

EPC

325

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

20

Kerala

Widening of road connecting from Kollam port to NH

Kollam

3

114

EPC

114

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

21

Kerala

Road from Payikulangara to Alappuzha bypass

Kochi

14

564

EPC

564

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

22

Kerala

Road from SH-Alappuzha bypass intersection

Kochi

12

672

EPC

672

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

23

Kerala

Road from Fort Vypin to Matysyafed Tourist Office

Kochi

9

375

EPC

375

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

24

Kerala

Road from Mudhiyam beach to Madhura bazaar

Beypore

12

300

EPC

300

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

25

Kerala

Road from Madhura bazaaar to Chullikad

Beypore

10

250

EPC

250

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

26

Kerala

Beypore road connectivity to Malaparamab beach

Beypore

18

450

EPC

450

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

27

Kerala

Road from Azhikkal to Puthuvalappu

Azhikkal

14

350

EPC

350

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

28

Kerala

Road from Payyabalam to Azhikkal

Azhikkal

12

300

EPC

300

DPR in progress. LAC proposal is likely to be submitted by 15th Sept.

29

Gujarat

Trapaj - Manar

Alang

6

150

EPC

150

DPR in progress.

30

Tamil Nadu

Development of dedicated Container Corridor to NHAI road for quick evacuation, Chennai

Chennai

8

280

EPC

280

DPR awarded recently and in progress.

31

Tamil Nadu

Connectivity to Katupalli through Ponnani

Katupalli

20

500

EPC

500

DPR awarded recently and in progress.

32

Tamil Nadu

Development of roads connectivity to Cuddalore Port - Sirkazhi Port

Cuddalore

10

350

EPC

350

DPR awarded recently and in progress.

33

Tamil Nadu

Road connectivity from Cuddalore port to NH-45A with RC over bridge

Cuddalore

3

155

EPC

155

DPR awarded recently and in progress.

34

Tamil Nadu

4 to 6 laning of NH-45B & NH-7A

Tuticorin

12

300

EPC

300

DPR awarded recently and in progress.

35

Andhra Pradesh

Guntur-Narakoduru-Tenali-Chandole-Nizampatnam Road

 

61

1525

 

 

DPR yet to be awarded